The world's first uhv hybrid dc project was started

On November 26, the 19th section of the HVDC transmission line of the udong DE power station transmission point of guangdong and guangxi uhv multi-terminal dc demonstration project was formally started in tower B51, lixi town, yingde city, guangdong, marking the world's first uhv hybrid dc line.The project starts from kunbei converter station in yunnan in the west, liubei converter station in guangxi in the east and longmen converter station in guangdong in the east.After the completion of the project, clean hydropower in yunnan will be directly transported to guangdong and guangxi.The project is scheduled to be put into operation in 2020 and put into operation in 2021. At that time, 8 million kWd channel power transmission capacity will be increased and the annual power transmission capacity will exceed 32 billion kWh.